Everything that prevents the project from happening as early as technically possible.

01

Desejos / Desires / Deseos / Желания

Commercial, political, financial or operational preferences that influence order without necessarily creating a technological dependency.

02

Paralisações / Interruptions

Calendars, holidays, shifts, imposed dates and intentional breaks that interrupt otherwise continuous production.

03

Recursos / Resources

Limits and timing of people, equipment, materials and financial resources required by production.

04

Construtibilidade / Constructability

Choices of methods, fronts and production sequences that may have alternatives and should not automatically become permanent logic.

05

Espaços / Spaces

Limited circulation, storage, access, unloading and maneuver areas that constrain simultaneous work.

06

Logística / Logistics

Transport, supply, access and operational routines that alter feasible sequences as conditions change.

Central distinction

A constraint can alter scheduling without being a physical or technological dependency. Liquid Scheduling tries to keep that distinction visible and reversible.